PRNC voices concerns about pollution at proposed Terminal One development

   POINT RICHMOND - The Point Richmond Neighborhood Council this week voiced serious concerns about pollution - and likely "inadequate" remediation efforts - at the proposed Terminal One residential project adjacent to Miller-Knox Regional Park and the Richmond Yacht Club.
     In a letter to the Richmond City Council, PRNC President Peter Thelin outlined a series of PRNC member concerns prompted by a presentation earlier in the month by Brian Lewis of the Brickyard Cove Alliance for Responsible Development (BCARD).
Aerial view of Terminal One location
     "We are concerned about potential discharges to the Bay and adjacent property; about protecting eel grass used by herring to spawn; and most particularly, about the safety to residents and public using this land in the future," Thelin wrote on behalf of the entire PRNC.
     "We have only one remaining chance to clean up this property correctly," he noted.
Thelin's letter came in the wake of a vote by the PRNC Dec. 3 to support the technical recommendations of the consultants to BCARD who have been studying the polluted site.
     Many of the recommendations, comments and findings of those consultants were outlined by Lewis at the meeting including concerns that Trichloroethylene (TCE) will remain at the site.
     "These findings strongly indicated the Remedial Design is inadequate to protect the Bay or adjacent RYC property," Thelin's letter to the council states.
     The Terminal One site is proposed by the Laconia Corporation of Walnut Creek to construct a 316-unit residential development on the former industrial site. It would include a combination of buildings including multi-story condominiums and single family bayside homes.
     A public waterfront park is also part of the project, though current plans show no public parking along the shoreline.
     The City of Richmond is also weighing whether to dip into city funds to help with increased costs of the Terminal One project.
     The funds would be used to help cover developer costs for handling seismic hazards, improvements to the Ferry Point Lift Station and development of the promised park.
     Last summer the proposed allocation of city funds included:


by Michael J. Fitzgerald, The Point

Sunday, February 24, 2019

Terminal One shoreline parking at issue

   POINT RICHMOND - The Bay Conservation and Development Commission's public hearing on the proposed 316-unit Terminal One housing project adjacent to the Richmond Yacht Club and Miller Knox Regional Park has been delayed until April.
     The BCDC has requested additional information about public parking from the developers of the project (Laconia) - and the City of Richmond.
Terminal One site, adjacent to the Richmond Yacht Club
     BCDC "asked the applicants to provide further information regarding the use of on-street parking as well as parking at nearly public access areas," Rebecca Coates-Muldoon of the BCDC said.
     Additionally, the BCDC wants to know of any measures being taken by the developers to "encourage public use for shoreline access and discourage use by residents and their guests."
     The delay in holding a public hearing to April may be partly an outgrowth of concerns raised by the Brickyard Cove Alliance for Responsible Development (BCARD) in addition to BCDC's analyses.
     In a letter to BCDC, BCARD member Brian Lewis outlined a series of the group's concerns about the proposed parking plan and existing parking issues. He included a video exhibit for BCDC to consider: BCARD video of traffic.
     "It will only be worse with the residents at Terminal One," he wrote,
     Of major concern is the planned lack of public parking along the proposed Shoreline Drive.
     "I suspect Terminal One is wanting to preserve the views from the homes and condos without cars," Lewis wrote, He noted that if it is allowed, it is a major change along the Point Richmond waterfront.
     "Every HOA in this area has on-street parking next to the water. Even San Francisco has street parking along the Embarcadero."
     Because the Terminal One project still needs finish up obtaining permits and is unlikely to receive them until fall of 2019, construction is now predicted to begin in 2021.

This map shows Shoreline Drive and the public park and pier.